• Wednesday, Aug 17, 2022
  • Last Update : 04:24 pm

Efforts underway to commission Rampal power plant in December

  • Published at 07:34 pm July 7th, 2021
Rampal
A bird's-eye view of Rampal power plant, a 1,320-megawatt coal-fired power station in Rampal upazila of Bagerhat district in Khulna Division Mahmud Hossain Opu

The first unit is designed to produce 660MW power

Bangladesh and Indian officials on Wednesday said they expect to commission the first unit of the joint-venture 1320MW Rampal Power Plant in December this year as scheduled.

"We expect the first unit of the plant to go on operation in December this year as per schedule . . . we are confident to meet the timeline," a Bangladesh power division official told BSS, a day after power secretaries of the two countries held a meeting virtually.

He said the first unit was designed to produce 660MW power while it was set to launch in December 2021 coinciding with the golden jubilee celebrations of Bangladesh's 1971 independence.


Also Read - Experts demand scrapping Rampal power plant


His comments came a day after Bangladesh's Power Secretary Md Habibur Rahman held an online meeting with his counterpart Alok Kumar on 1320MW Maitree Power project while the cross-country conference was joined by concerned ministries and agencies of the two countries.

India's Power Ministry later in a statement said the two officials discussed and identified some "certain critical issues" to address for the timely commission of the coal-fired thermal plant, said to be an ultra-super one in terms of technology and efficiency to protect the environment.

Indian experts are constructing the plant in Bangladesh under a power sharing agreement between Bharat Heavy Electricals Limited (BHEL) and Bangladesh India Friendship Power Company Limited (BIFPCL).


Also Read - PM Hasina approves scrapping of 10 coal-fired power plant projects


“We are providing necessary support for completion of the project in time,” Bangladesh's power division official said.

The Indian statement said the second unit of the plant was expected to be commissioned along with the implementation of the associated transmission system.

"Since March 2020, the Covid situation exposed the people of both the countries to a new challenge along with affecting the implementation of the Maitree project. Now both the sides are putting the best effort to complete the project in time," it read.