• Thursday, Aug 18, 2022
  • Last Update : 04:24 pm

Construction works of Teesta Bridge going on in full swing

  • Published at 03:06 pm April 25th, 2021
Teesta Bridge
The construction works of the Teesta Bridge is undergoing and expected to be finished in June 2023 BSS

The work is expected to be finished in June 2023

The construction works of the much-awaited Teesta Bridge over the Teesta River is going on in full swing.

Officials said Local Government Engineering Department (LGED) is constructing the girder bridge at a cost of Tk367 crore which was provided by the government of Bangladesh and Saudi Fund for Development of KSA jointly.

Earlier, the feasibility study to construct the bridge was done by the experts' team of Water and Flood Management Institute of Bangladesh University of Engineering and Technology (Buet) led by Prof Sajib Kumar Bala and Prof Dr Tariqul Islam in 2010 and 2011, they said.

An executive engineer of LGED said the 1490-metre long bridge would be constructed over the Teesta River between Horipurghat of Sundarganj upazila in Gaibandha and Chilmari Kheyaghat point of Chilmari upazila in Kurigram at the direct supervision of the LGED.

Meanwhile, 68.34 hectares of land at Gaibandha point and 22.50 hectares of land at Kurigram point had already been acquired for making the connecting roads at both sides of the bridge.

Besides, an 86-km long spacious road from the bridge would also be connected to the Rangpur-Bogra Highway in Dhaperhat area under Sadullapur upazila via Lakshmipur-Sadullapur upazila town to avoid severe traffic jam in Gaibandha district town, said an official.

Talking to the BSS, LGED Executive Engineer Ahsan Kabir said the girder bridge would have 30 pillars and the piling work of the pillars has been progressing fast.

The work would be finished in June 2023, he expected.